Dry Dock Diary – Part 11 – 28th June

Work on TS Queen Mary, alongside Garvel Clyde’s lay-by berth, is almost complete. (1) Small areas of unfinished paint work were completed, including: the trunking between the funnels, the bulwark in way of the bridge and touch ups to the Captain’s cabin. (2) The ship’s timber windows

Read more

Dry Dock Diary – Part 10 – 24th June

Work continues apace alongside the Garvel Clyde lay-by berth. (1) Small areas not blasted were picked up with manual discing over the weekend, and the ship actively ventilated and dried (2) Painting of the external structures is complete, with the following now fully prepped and coated: –

Read more

Dry Dock Diary – Part 9 – 23rd June

Work continues apace alongside the Garvel Clyde lay-by berth. – Internal blasting completed on Friday 21st June (so far as the blasters were able to access) and you can see in one photo the impact this has had on the ship’s lower deck plates. Any small areas

Read more