Work continues apace alongside the Garvel Clyde lay-by berth. – The primary task is the completion of all internal blasting, which is now well underway – The huge amount of debris that has been blasted is being cleared up, so that painters can tackle any small areas
Read more →This report captures all work on 17th and 18th June. June 17th: – UHP blasting progressed inside the vessel, with work concentrated in the lower deck (shaft space and kitchen space) and Queens’ Restaurant – TS Queen Mary’s new 2D steel lettering was welded in place, undercoated
Read more →Work at Garvel Clyde continues to progress well. This report captures all work from Thursday 13th to Sunday 16th. – UHP blasting progressed inside the vessel, with work concentrated in the old observation gallery space (prom deck aft), main deck (Firth Lounge) and lower deck (shaft space)
Read more →