Dry Dock Diary – Part 9 – 23rd June

Work continues apace alongside the Garvel Clyde lay-by berth. – Internal blasting completed on Friday 21st June (so far as the blasters were able to access) and you can see in one photo the impact this has had on the ship’s lower deck plates. Any small areas

Read more

Dry Dock Diary – Part 8 – 19th June

Work continues apace alongside the Garvel Clyde lay-by berth. – The primary task is the completion of all internal blasting, which is now well underway – The huge amount of debris that has been blasted is being cleared up, so that painters can tackle any small areas

Read more

Dry Dock Diary – Part 7 – 18th June

This report captures all work on 17th and 18th June. June 17th: – UHP blasting progressed inside the vessel, with work concentrated in the lower deck (shaft space and kitchen space) and Queens’ Restaurant – TS Queen Mary’s new 2D steel lettering was welded in place, undercoated

Read more