Work continues apace alongside the Garvel Clyde lay-by berth. (1) Small areas not blasted were picked up with manual discing over the weekend, and the ship actively ventilated and dried (2) Painting of the external structures is complete, with the following now fully prepped and coated: –
Read more →Work continues apace alongside the Garvel Clyde lay-by berth. – Internal blasting completed on Friday 21st June (so far as the blasters were able to access) and you can see in one photo the impact this has had on the ship’s lower deck plates. Any small areas
Read more →Work continues apace alongside the Garvel Clyde lay-by berth. – The primary task is the completion of all internal blasting, which is now well underway – The huge amount of debris that has been blasted is being cleared up, so that painters can tackle any small areas
Read more →