Dry Dock Diary – Part 7 – 18th June

This report captures all work on 17th and 18th June. June 17th: – UHP blasting progressed inside the vessel, with work concentrated in the lower deck (shaft space and kitchen space) and Queens’ Restaurant – TS Queen Mary’s new 2D steel lettering was welded in place, undercoated

Read more

Dry Dock Diary – Part 6 – 17th June

Work at Garvel Clyde continues to progress well. This report captures all work from Thursday 13th to Sunday 16th. – UHP blasting progressed inside the vessel, with work concentrated in the old observation gallery space (prom deck aft), main deck (Firth Lounge) and lower deck (shaft space)

Read more

Dry Dock Diary – Part 5 – 13th June

Work at Garvel Clyde is progressing well. Yesterday started with a meeting between the surveyor and our naval architect, the outcome of which was very positive. As that meeting was underway, work in the dock itself was continuing apace: – UHP blasting of the superstructure was completed